The work lasted barely 36 hours: two bridges were demolished in one weekend on the A7 in Marseille

The work lasted barely 36 hours: two bridges were demolished in one weekend on the A7 in Marseille

International 14/06/2026 BFM TV 👁 20
⚡ Quick Summary

The Hermitage bridge and the Brugas footbridge were destroyed, the area was cleaned and the roadway rehabilitated within 36 hours.